Road project information


Weatherford Democrat

— Aledo Trail

Work on the Aledo Trail couplet has been delayed due to a conflict with AT&T lines, according to county sources. The conflict is not expected to be resolved until late October or November.   



FM Road 1187

TxDOT officials and crews with McMahon Contracting have set the week of Sept. 23 as the week in which traffic will be switched on FM 1187. Currently traffic is running on two lanes on the west side of FM 1187 as crews excavate and rebuild the two lanes on the east side. During the week of Sept. 23, traffic is expected to be moved over to the new lanes on the east side of FM 1187, allowing crews to begin excavating and rebuilding the west side of FM 1187.